Open the pressure relief valve on the vacuum pump. This
allows the major contaminants from the sealed system to
escape into the atmosphere rather than enter the oil in the
vacuum pump.
Both the low and high side valves on the compound gauge set
should be opened and the vacuum pump turned on.
After five minutes, close the pressure relief valve on the
vacuum pump. Check the blue gauge after running the vacuum
pump for 10 minutes. A vacuum reading of zero to 10 inches
would indicate a leak in the system or the hose connections.
Check all hose connections for tightness. If the low side gauge
does not change, there is a leak in the sealed system. Locate
the leak and correct it before proceeding.
If the blue low side gauge is well below 10 inches of vacuum,
continue the evacuation for at least 40 to 45 minutes or until
you have a dry systemyou have a dry system
you have a dry systemyou have a dry system
you have a dry system.
SERVICE
GAUGES
RED HOSE
BLUE HOSE
YELLOW
HOSE
VACUUM
PUMP
SERVICE
GAUGES
CHARGE
CYLINDER
ELECTRONIC
LEAK DETECTOR
YELLOW
HOSE
RED
HOSE
BLUE
HOSE
At this time there should be a good, deep evacuation, or dry
atmosphere inside the sealed system. Close both the low and
high side valves on the compound gauge set and turn off the
vacuum pump.
Disconnect the yellow colored hose at the vacuum pump and
connect it to the bottom port or connection on the charging
cylinder. Open the valve on the cylinder.
For the correct amount of R-22 refrigerant charge, check the
data plate of the air conditioner you are working on. To
compensate for the red liquid line, on the gauge set (approx.
30—36 inches long), add one ounce to the data plate amount.
You are now ready to do a weighted charge.
The air conditioner charge is critical and must be exact for
proper cooling.
Allow the refrigerant charge to equalize by waiting 10 minutes
before starting the system. After 10 minutes, do a cooling
performance test to determine whether the problem was in the
amount of charge or within the components of the system.
Now the blue low side and the red high side lines should be
disconnected. Make sure that the air conditioner connection is
sealed before removing the lines. The process tube can be
pinched off in two places; the charging port cut off, and the end
of the tube brazed for a hermetically sealed system.
SERVICE